Herald Park Phase II
Next to Crewe station Herald Park is a restricted site in the heart of town.
A steel framed structure with concrete floors, metal roof, brick façade and aluminium windows.
Built in the same style as Phase 1, with a floor area of 20,000sq feet spread across three floors this was the second of two phases built by Ocon on the same site.
The building has a feature entrance that acts as a circulation hub.
The office is open plan with raised access computer floors throughout. There are toilets on each floor and a shower facility on the 1st floor.
Attractive external landscaping includes controlled car parking for 50 cars and a cycle store for 10 cycles.
Project Team
Client: DCP (Crewe) Limited
Architect: Hartington, Flemming & Worsley
Engineer: Tier Consulting
PQS: Tozer & Tozer
Form of Contract: JCT Design & Build 2005
Contract Period: 37 weeks
Value: £2.1m